List problems that may occur for the contractor during construction when the actual quantity of work is lower than the pay quantities in the bid documents

+1
Answers (1)
  1. 26 June, 12:38
    0
    problems that may occur for the contractor during construction when the actual quantity of work is lower than the pay quantities in the bid documents are unbalanced bids in unit prices on which periodic payment estimates are based. change orders subject to negotiated payments changes in design or construction technology incentives for early completion
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “List problems that may occur for the contractor during construction when the actual quantity of work is lower than the pay quantities in ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.