Chico's Clockworks uses job order costing for its custom clock-making business. Job GF1260 is a custom-made grandfather clock. Chico's job cost sheet for Job GF1260 shows a total cost of $4,265, including direct labor of 50 hours at $20 per hour. Overhead is applied at 100% of direct labor cost. What is the direct materials cost for Job GF1260? A : $3,455 B : $1,000 C : $2,265 D : $2,895

+3
Answers (1)
  1. 19 February, 19:28
    0
    Option C,$2,265, is correct

    Explanation:

    Labor cost = direct labor hours*rate per hour

    direct labor hours is 50 hours

    direct labor cost per hour is $20

    labor cost=50*$20=$1,000

    Overhead was applied as 100% of direct labor cost

    overhead=100%*$1000=$1000

    Total cost of job=direct material cost+direct labor+overhead

    direct material cost=total cost-direct labor-overhead

    direct material cost=$4,265-$1000-$1000=$2,265

    The correct option is C,$2,265
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Chico's Clockworks uses job order costing for its custom clock-making business. Job GF1260 is a custom-made grandfather clock. Chico's job ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.