The total completion time on a project is 25 days. Task A is planned to take seven days while Task B is planned for five days and Task C is planned to take eight days. The tasks have a serial relationship. How much slack does the project have?
A) Negative 5 days slack.
B) Positive 5 days slack.
C) Positive 17 days slack.
D) Positive 3 days slack.
+5
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The total completion time on a project is 25 days. Task A is planned to take seven days while Task B is planned for five days and Task C is ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.