Dallas Company uses a job order costing system. The company's executives estimated that direct labor would be $5,130,000 (190,000 hours at $27/hour) and that factory overhead would be $1,430,000 for the current period. At the end of the period, the records show that there had been 110,000 hours of direct labor and $1,130,000 of actual overhead costs. Using direct labor hours as a base, what was the predetermined overhead rate? a. $5.17 per direct labor hour. b. $7.00 per direct labor hour. c. $6.42 per direct labor hour. d. $5.84 per direct labor hour. e. $6.25 per direct labor hour.

+4
Answers (1)
  1. 26 March, 23:49
    0
    Estimated manufacturing overhead rate = $7.53 per direct labor hour

    Explanation:

    Giving the following information:

    The company's executives estimated that direct labor would be $5,130,000 (190,000 hours at $27/hour) and that factory overhead would be $1,430,000 for the current period.

    We need to use the following formula:

    Estimated manufacturing overhead rate = total estimated overhead costs for the period / total amount of allocation base

    Estimated manufacturing overhead rate = 1,430,000/190,000 = $7.53 per direct labor hour
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Dallas Company uses a job order costing system. The company's executives estimated that direct labor would be $5,130,000 (190,000 hours at ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.