For Culver Company, units to be produced are 5,590 in quarter 1 and 6,600 in quarter 2. It takes 2.0 hours to make a finished unit, and the expected hourly wage rate is $16 per hour. Prepare a direct labor budget by quarters for the 6 months ending June 30, 2017.

+1
Answers (1)
  1. 15 February, 23:26
    0
    The preparation of the direct labor budget is shown below:

    Culver Company

    Direct labor budget for six months

    June 30, 2017

    Particulars Quarter 1 Quarter 2 Six month

    Production

    units (A) 5,590 6,600

    Direct labor

    Hours (B) 2.0 2.0

    Labor wage

    rate per hour (C) $16 $16

    Total labor cost (A * B * C) $178,880 $211,200 $390,080

    Six month is a sum of quarter 1 and quarter 2
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “For Culver Company, units to be produced are 5,590 in quarter 1 and 6,600 in quarter 2. It takes 2.0 hours to make a finished unit, and the ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers