Ask Question
12 March, 00:58

Crane Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1450000 each quarter. The total contract price is $18168000 and Crane estimates total costs of $17250000. Crane estimates that the building will take 3 years to complete, and commences construction on January 2, 2018. At December 31, 2018, Seasons estimates that it is 30% complete with the construction, based on costs incurred. What is the total amount of Revenue and Profit from Long-Term Contracts recognized for 2018?

+1
Answers (1)
  1. 12 March, 03:23
    0
    Revenue recognized for 2018 is $5,450,400

    Profit for the same year is $275,400

    Explanation:

    The is a method of revenue recognition known as cost to completion. It is used to recognize revenue from long term projects which are mostly construction contracts that will not be completed in a year. In this system, the revenue to be recognized is a function of the cost.

    As such, where 30% of the total cost of the project is incurred in the first year, 30% of the total revenue will also be recognized in the first year. The difference between the revenue and the cost gives the profit.

    Given that total revenue for 3 years is $18168000

    Revenue to be recognized

    = 30/100 * $18,168,000

    = $5,450,400

    Cost incurred

    = 30/100 * $17,250,000

    = $5,175,000

    Profit for 2018

    = $5,450,400 - $5,175,000

    = $275,400
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Crane Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion method. The ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers