The predetermined manufacturing overhead rate for the year was 140% of direct labor cost; employees were paid $17.50 per hour. If the estimated direct labor hours were 15,000, what was the estimated manufacturing overhead? A. $210,000. B. $187,500. C. $262,500. D. $367,500.
+4
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The predetermined manufacturing overhead rate for the year was 140% of direct labor cost; employees were paid $17.50 per hour. If the ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Home » Business » The predetermined manufacturing overhead rate for the year was 140% of direct labor cost; employees were paid $17.50 per hour. If the estimated direct labor hours were 15,000, what was the estimated manufacturing overhead? A. $210,000. B. $187,500.