Ask Question
5 December, 02:39

In order to avoid project delays, project managers confronted with a resource overload will seek to delay some of the noncritical activities by an amount no more than their slack period, to level the demand for that worker.

a. True

b. False

+1
Answers (1)
  1. 5 December, 05:09
    0
    Answer: True

    Explanation:

    When a project manager is confronted with resource overload, an activity that is not on the critical path can be delayed in order not to unnecessarily delay the project. The non-critcal activities can be delayed than an amount no longer than the slack period. This levels demand for that worker.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “In order to avoid project delays, project managers confronted with a resource overload will seek to delay some of the noncritical ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers