The process of reviewing all change requests, approving changes, and managing changes to deliverables, organizational process assets, project documents and project management plan; and communicating their disposition, is known as:

+5
Answers (1)
  1. 9 November, 10:46
    0
    Perform Integrated Change Control

    Explanation:

    Perform Integrated Change Control is the process of reviewing all change requests; approving changes and managing changes to deliverable, organizational process assets, project documents, and the project management plan; and communicating their disposition.

    It reviews all requests for changes or modifications to project documents, deliverable, baselines, or the project management plan and approves or rejects the changes
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The process of reviewing all change requests, approving changes, and managing changes to deliverables, organizational process assets, ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers