Resource-limited scheduling is a method for developing the shortest schedule when the quantity of resources is fixed. It will shorten the project completion time if necessary.

a. True

b. False

+4
Answers (2)
  1. 19 May, 13:51
    0
    True

    Explanation:

    Habitat fragmentation is the method used to develop the shortest possible schedule for a project when the amount of available resource is fixed. It is a technique used by project managers in order to modify implementing a project as well as it's date of completion.
  2. 19 May, 14:15
    0
    True

    Explanation

    Resource leveling, or smoothing, is a method for developing a schedule that attempts to minimize the how requirements for resources are manged when the project completion time is fixed. Resource-limited scheduling is a method created for the sole purpose of coming up with a plan to create the shortest schedule; when the quantity of available resources is fixed and also when there might be an extension of the project completion time in order to keep within the resource limits.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Resource-limited scheduling is a method for developing the shortest schedule when the quantity of resources is fixed. It will shorten the ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers