Refresh produces soft drinks and sodas. Production of 100,000 liters was started in February, 85,000 liters were completed. Material costs were $38,220 for the month while conversion costs were $16,380. There was no beginning work-in-process; the ending work-in-process was 40% complete. What is the cost of the product that was completed and transferred to finished goods?

+5
Answers (1)
  1. 19 September, 19:48
    0
    Cost transfered to finished goods = $51,000

    Explanation:

    In this production process the target production was 100,000 litres. In February 85,000 litres was completed.

    So the balance uncompleted is 100,000 - 85,000 = 15,000 litres

    Of this 15,000 40% was eventually completed. That is 0.4 * 15,000 = 6,000 litres

    Therefore

    Equivalent production = 85,000 + 6,000

    Equivalent production = 91,000 litres

    Cost per litre = (Material cost + Conversion cost) / Number of litres

    Cost per litre = (38,220+16,380) / 91,000

    Cost per litre = 54,600/91,000 = $0.6

    Cost transfered to finished goods = Cost per litre * Completed goods

    Cost transfered to finished goods=0.6 * 85,000

    Cost transfered to finished goods = $51,000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Refresh produces soft drinks and sodas. Production of 100,000 liters was started in February, 85,000 liters were completed. Material costs ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.