A company has contracted with an outside vendor to perform a service that will provide hardware, software, and procedures in case of a catastrophic failure of the primary datacenter. The Chief Information Officer (CIO) is concerned because this contract does not include a long-term strategy for extended outages.

Which of the following should the CIO complete?

A. Disaster recovery plan

B. Business continuity plan

C. Service level agreement

D. First responder training

+3
Answers (1)
  1. 20 August, 00:36
    0
    Answer: Option (b) is correct.

    In the following scenario Chief Information Officer is perturbed because the agreement does not include a strategy (long-term) for extended outages. Therefore, in such case the CIO should complete Business continuity plan.

    Business continuity planning can be referred to as the technique which is responsible for creating a structure of thwarting and recuperation from potential threats to a organization.

    The plan assure that work force and assets are secured and can function rapidly at times of a disaster. The plan is usually apprehended in advance and includes input from stakeholders.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A company has contracted with an outside vendor to perform a service that will provide hardware, software, and procedures in case of a ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.