Ask Question
31 July, 19:26

Based on predicted production of 23,000 units, a company anticipates $414,000 of fixed costs and $362,250 of variable costs. The flexible budget amounts of fixed and variable costs for 21,000 units are (Do not round intermediate calculations) : Multiple Choice $330,750 fixed and $414,000 variable. $414,000 fixed and $330,750 variable. $414,000 fixed and $362,250 variable. $378,000 fixed and $330,750 variable. $378,000 fixed and $362,250 variable.

+1
Answers (1)
  1. 31 July, 22:30
    0
    The correct option is a. the variable cost is $330,750 and fixed cost is $414,000.

    Explanation:

    For computing the correct figures of variable cost and fixed cost for 21,000 units, first we have to calculate the variable cost per unit.

    So,

    Variable cost per unit = Total variable cost : Number of units

    = $362,250 : 23,000

    = $15.75 per unit

    SO, variable cost for 21,000 units = Number of units * per unit price

    = 21,000 * $15.75

    = $330,750

    Hence, the variable cost for 21,000 units is $330,750

    Since the fixed cost remained fixed whether production level is increased or not. So, fixed cost would be $414,000

    Therefore, the correct option is a. the variable cost is $330,750 and fixed cost is $414,000.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Based on predicted production of 23,000 units, a company anticipates $414,000 of fixed costs and $362,250 of variable costs. The flexible ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers