Shipments of product X from a plant to a wholesaler are made in lots of 600 units. The wholesaler's average demand for product X is 150 units per week. Lead time from plant to wholesaler is 4 weeks. The wholesaler pays for the shipments when they leave the plant. What is the total of the wholesaler's cycle inventory and pipeline inventory?
+3
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Shipments of product X from a plant to a wholesaler are made in lots of 600 units. The wholesaler's average demand for product X is 150 ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.