A product's standard cost card specifies that a unit of the product requires 4 direct labor-hours. During September, 3,350 units were made, which was 150 units less than budgeted. The total budgeted direct labor cost for September was $117,600. The direct labor cost incurred during September was $111,850 and 13,450 direct labor-hours were worked.

The labor rate variance for the month was:

a) $5750 F

b) $1130 U

c) $5750 U

d) $1130 F

+1
Answers (1)
  1. 5 February, 10:09
    0
    Direct labor rate variance = $1,130 favorable

    Explanation:

    Giving the following information:

    Standard:

    A unit of the product requires 4 direct labor-hours.

    Budgeted production = 3,500 units

    Budgeted direct labor cost = 117,600

    Direct labor rate per hour = 117,600 / (3,500*4) = $8.4 per hour

    Actual:

    Production = 3,350 units

    Direct labor cost = 111,850

    Direct labor hours = 13,450

    Direct labor rate per hour = 111,850/13,450 = $8.31598 per hour

    To calculate the direct labor rate variance, we need to use the following formula:

    Direct labor rate variance = (Standard Rate - Actual Rate) * Actual Quantity

    Direct labor rate variance = (8.4 - 8.31598) * 13,450

    Direct labor rate variance = $1,130 favorable
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A product's standard cost card specifies that a unit of the product requires 4 direct labor-hours. During September, 3,350 units were made, ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.