When a firm has flotation costs equal to 6.8 percent of the funding need, project analysts should:?

+4
Answers (1)
  1. 14 September, 21:50
    0
    When a firm has flotation costs equal to 6.8 percent of the funding need, project analysts should increase the initial project cost by dividing that cost by (1-0.068). The flotation cost is the cost which emerge when a corporation gather its fund by issuing new securities. Underwriting fees, legal fees, registration fees are the common fees that will increase corporate's expense when they issue securities. Therefore, we can consider those fees as a flotation cost.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “When a firm has flotation costs equal to 6.8 percent of the funding need, project analysts should:? ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.