Consider the steps in a bicycle-factory assembly line: Step 1: rate = 120 handlebars per hour Step 2: rate = 60 sets of wheels per hour Step 3: rate = 240 seats per hour What is the fastest rate at which the assembly line can produce complete bicycles?

+2
Answers (2)
  1. 9 January, 05:47
    0
    60 bicycles

    Explanation:

    The slowest step determines the overall rate of the process.
  2. 9 January, 08:09
    0
    Answer:60 and slowest determines overall

    Explanation:

    I took the warm up assignment
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Consider the steps in a bicycle-factory assembly line: Step 1: rate = 120 handlebars per hour Step 2: rate = 60 sets of wheels per hour ...” in 📘 Chemistry if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.