Which of the following strategies should the Government NOT consider during IP implementation?

a. Consider data rights as a? priced option? to the contract.

b. Negotiate data rights after a contractor has been notified of selection.

c. Outline the Government's data rights needs in the RFP.

d. Make technical data rights a source selection criterion

+5
Answers (1)
  1. 23 July, 03:41
    0
    Correct answer is (b). Negotiate data rights after a contractor has been notified of selection.

    Explanation:

    During IP implementation, it is expedient for government to outline and negotiate the data before selection and notification of contractor to ensure effective planning.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Which of the following strategies should the Government NOT consider during IP implementation? a. Consider data rights as a? priced option? ...” in 📘 History if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.