Josh finished 3/5 th part of his painting job. he said he will need 8 more days to finish remaining job. How many days he took in total to finish his painting job completely?

+3
Answers (1)
  1. 30 October, 09:15
    0
    Are there any choices
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Josh finished 3/5 th part of his painting job. he said he will need 8 more days to finish remaining job. How many days he took in total to ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.