In the haden company, the standard material cost for the silk used in making a dress is $27.00 based on three square feet of silk at a cost of $9.00 per square foot. the production of 1,000 dresses resulted in the use of 3,400 square feet of silk at a cost of $9.20 per square foot. the materials quantity variance is

+5
Answers (1)
  1. 10 March, 02:17
    0
    To solve for the materials quantity variance, we have the formula below:

    Materials Quantity Variance = (Actual Quantity Used * Standard Rate) - (Standard Quantity Allowed * Standard Rate)

    The solution is shown below:

    Materials Quantity Variance = ($9.20 - $9.00) * 3400

    Materials Quantity Variance = $680

    The answer is $680.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “In the haden company, the standard material cost for the silk used in making a dress is $27.00 based on three square feet of silk at a cost ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.