a engineer has started to create a model in 27 days. 1/6 of the model is complete. how many days will it take to complete the model?

+3
Answers (1)
  1. 21 September, 07:59
    0
    It would take 22 1/2 days:

    1/6 of 27 = 4.5 days

    4.5x5 = 22.5
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “a engineer has started to create a model in 27 days. 1/6 of the model is complete. how many days will it take to complete the model? ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.