It took $4$ days for $75$ workers, all working together at the same rate, to build an embankment. If only $50$ workers had been available, how many total days would it have taken to build the embankment?

+5
Answers (1)
  1. 11 November, 14:58
    0
    2.67 days

    Step-by-step explanation:

    75/4=18.75

    18.75/50=2.67
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “It took $4$ days for $75$ workers, all working together at the same rate, to build an embankment. If only $50$ workers had been available, ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.