If 15 workers did a job is 8 hours, how long would it take 5 workers to do half of this job?

+5
Answers (2)
  1. 1 February, 20:28
    0
    Since 15 workers did 8 hours of work, the total amount of work needed is 120 hours. Half of this job would be 60 hours. Then divide this amount by the 5 workers doing the job. This would make the job 12 hours
  2. 1 February, 21:11
    0
    J=15w*8h=120 (worker*hours)

    5h=120/2

    5h=60

    h=12 hours
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “If 15 workers did a job is 8 hours, how long would it take 5 workers to do half of this job? ...” in 📘 Mathematics if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.