Which of the following responses identifies a common type of logical dependency used to sequence project activities?

a. last-in; last-out

b. finish-to-start

c. first-in; first-out

d. last-in; first-out

+1
Answers (1)
  1. Today, 03:32
    0
    b. finish-to-start

    Explanation:

    Activity dependencies or activity relationships are of four types.

    Finish-to-Start: Activity B cannot start until the activity A finishes. Start-to-Start: The activity B cannot start until the activity A starts. Start-to-Finish: The activity B cannot finish until the activity A starts. Finish-to-Finish: The activity B cannot finish until the activity A finishes.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Which of the following responses identifies a common type of logical dependency used to sequence project activities? a. last-in; last-out ...” in 📘 Social Studies if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers