Rob is responsible for estimating a work package that has a significant amount of uncertainty associated with the time and cost to complete. Due to the uncertainty involved he will be making a low, an average and a high estimate. Rob is using which estimating approach?

+1
Answers (1)
  1. Today, 02:10
    0
    Range estimating.

    Explanation:

    Range estimation is an estimation approach that allows an interested person to have much relevant information about the nature of a task being set. Through this estimate it is possible to have more confidence or more uncertainty in a project that is being stipulated and that may result in a large profit or a great loss.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Rob is responsible for estimating a work package that has a significant amount of uncertainty associated with the time and cost to ...” in 📘 Social Studies if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers