Vanguard has an overall (composite) WACC of 10%, which reflects the cost of capital for its average asset. Its assets vary widely in risk, and Vanguard evaluates low-risk projects with a WACC of 8%, average-risk projects at 10%, and high-risk projects at 12%. The company is considering the following projects:Col1 Project A B C DCol2 Risk High Average High Low Col3 Expected Return 15% 12% 11% 9%Which set of projects would maximize shareholder wealth?

+1
Answers (1)
  1. 15 September, 15:56
    0
    The projects which maximize Vanguard's shareholder wealth are Project A; Project B; Project D.

    Explanation:

    Projects which maximize the shareholder value are projects delivering Expected Returns which are higher than its risk-adjusted weighted average cost of capital (WACC).

    As a result, Project A with Expected return of 15% and risk adjusted WACC of 12%; Project B with Expected return of 12% and risk adjusted WACC of 10%; Project D with Expected return of 9% and risk adjusted WACC of 8%; are the projects that maximize the shareholder's value.

    On the other hand, Project C with Expected return of 11% and risk adjusted WACC of 12% is harmful to shareholder value.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Vanguard has an overall (composite) WACC of 10%, which reflects the cost of capital for its average asset. Its assets vary widely in risk, ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.