An architect is considering bidding for the design of a new shopping mall. The cost of drawing plans and submitting a model is $10,000. The probability of being awarded the bid is 0.12, and anticipated profits are $100,000, resulting in a possible gain of this amount minus the $10,000 cost for plans and a model. What is the expected value in this situation?

+1
Answers (1)
  1. 16 February, 00:36
    0
    The expected value is $2,000

    Explanation:

    The expected value in the following situation is computed as:

    Expected value = Probability of bid * (Anticipated Profits - Cost of drawing plans) - (1 - Probability of bid) * Cost of drawing plans

    where

    Probability of bid is 0.12

    Anticipated Profits is $100,000

    Cost of drawing plans is $10,000

    Putting the values above:

    = 0.12 * ($100,000 - $10,000) - (1 - 0.12) * $10,000

    = 0.12 * $90,000 - 0.88 * $10,000

    = $10,800 - $8,800

    = $2,000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “An architect is considering bidding for the design of a new shopping mall. The cost of drawing plans and submitting a model is $10,000. The ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.