    A variance is favorable when the actual costs or actual quantity were lower than estimated.

    Explanation:

    We weren't provided with enough information to calculate each variance. I will provide with the formulas.

    Variable manufacturing overhead rate (cost) variance = (standard rate - actual rate) * actual quantity

    Variable overhead efficiency variance = (Standard Quantity - Actual Quantity) * Standard rate

    Fixed overhead spending variance = (actual fixed overhead costs - allocated fixed overhead)

    Manufacturing overhead volume variance = (Estimated manufacturing overhead rate*budgeted allocation base) - (Estimated manufacturing overhead rate * Actual amount of allocation base)

    A variance is favorable when the actual costs or actual quantity were lower than estimated.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Compute the overhead variances for the month: variable overhead cost variance, variable overhead efficiency variance, fixed overhead cost ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.